Subcontracts and Subcontractor Claims
  1. Knowledge Base
  2. Payment Claims
  3. Subcontracts and Subcontractor Claims

Link Onsite & Offsite Materials from a Sub contractor Claim

You can link any costs that flow through on a Sub contractor's claim as Onsite or Offsite materials.

Introduction

Sub Contract Onsite / Offsite Items in Trade Summary Lines

Sub Contract View of Onsite / Offsite Amounts

Approve Sub Contractor Invoices for Offsite / Onsite Materials


Introduction

In a Sub contract, you can mark all or part of a Trade Summary line or Invoice line as Onsite or Offsite. These amounts can then be included in the next claim for your Project.

Return to Top of Page


Sub Contract Onsite / Offsite Items in Trade Summary Lines

In a Sub contract, you can specify part of the amount of a Trade Summary line as Onsite / Offsite.

  • Start at Payment Claims > Sub contract.
  • Select the Sub contract you want.

On the Contract tab:

On the Trade Summary line that you want to mark as Onsite or Offsite:

  • Click the value in the On/Off Site column.

Subcontract-onsite-offsite

 

In the Onsite/Offsite Item window:

  • Type: Select On site or Off site from the dropdown list.
  • Description: Enter a description for the item.
  • Amount: Enter the amount that relates to this item.
  • Click Add, then click Finish.

Subcontract-onsite-offsite-TS line-10555-4

 

Back on the Edit Sub contract screen, you can now see the amount you have flagged as Offsite.

  • Click Save.

Subcontract-onsite-offsite-added-10555-5

Return to Top of Page


Sub Contract View of Onsite / Offsite Amounts

In a Sub Contract you can view and edit any lines that have Onsite / Offsite amounts.

  • Start at Payment Claims > Sub contract and select the Sub contract you want.

On the Contract tab:

Cost code: Click the O icon O icon for Cost code onsite offsite-10555-6 above this field.

 

Subcontract onsite offsite items screen via O-10555-6

 

In the Onsite/Offsite Items window, you can view and edit any items, and attached documents to a line.

  • Double click a line to edit it.
  • Click the Document icon Document icon to add supporting documents.
  • Click Finish.

sub contract onsite offsite via O 10555-7

Return to Top of Page


Approve Sub Contractor Invoices for Offsite / Onsite Materials

If all or part of the materials on a Sub Contractor invoice are held Offsite / Onsite, you can now record this for the Invoice line and relate it to the relevant Cost Code so it can be included in your next claim.

  • Start at Payment Claims > Approve.
  • Select the Invoice to approve and go to the Invoice Lines.

In the Invoice lines section:

  • Click Add Offsite materials.
add offsite materials-1

 

In the Onsite/Offsite Item window:

  • Type: Select On site or Off site from the dropdown list.
  • Description: Enter a description for the item.
  • Amount: Enter the amount that relates to this item.
  • Click Save.

Subcontract-onsite-offsite ts line 10555

Return to Top of Page


Need more help? We’re here! We hope our article was helpful! If you need more info or want to connect, drop us an email at support@lentune.com.

Thank you. We love to hear from you!

Last updated: 15 February 2024